Center Avenue Waterline Project on Track, Quality Testing Underway

MDOT Slated to Begin Paving Soon, Aims for Cleanup in November

June 20, 2009       Leave a Comment
By: Dave Rogers

Printer Friendly Story View

Work continues along Center Avenue in Bay City.
(MyBayCity Photo Courtesy of City of Bay City)

Contrary to rumors, work has not been suspended on the Center Avenue water-sewer project.

However, work is slowed while waterlines that have been installed are being tested.

City residents are destined to have to deal with construction on Center Avenue until mid-November.

The Michigan Department of Transportation (MDOT) and contractor Six S Contracting of Waterford, in north Oakland County, are coordinating closely with city officials and local residents to minimize traffic problems and access to homes.

The project supervised by the Michigan Department of Transportation (MDOT) is eliminating two parallel six inch cast iron water mains that are more than 100 years old. A single 12 inch ductile iron water main will replace the old mains. The city will replace water service with copper pipe from the water main to the curb stop shutoff in front of each house. The contractor will connect to the existing water service pipe. the homeowner is responsible for the portion of the water service from the city curb stop to inside the house.

City sources have released the following information as a service to residents and local travelers:

  • Water purity tests are expected to take about two weeks; then water connections to individual properties will be made.

  • Concrete will be removed in the two westbound (north) lanes proceeding east from Johnson during the last two weeks of July. Property owners can reopen their drive approaches with temporary ramps, taking care to avoid damaging gas lines buried a foot deep.

  • Paving will be done in late June through mid-July on the two eastbound (south) lanes, drive approaches and intersections.

  • Paving of the two westbound (north) lanes is scheduled mid-August through mid-October.

  • Work will continue on intersections, some of which will be closed.

  • The center lane will be the last to be paved and will be colored and stamped to resemble brick.

  • Cleanup will occur mid-October through mid-November.

  • The road is slated to open to all traffic by mid-November.

    Status of intersections is as follows: Carroll, closed until reconstructed; Center Court, open; Green, closed until reconstructed; Hayes Drive, remains open; Johnson, open; Livingston, open; Park, open; Pendleton, closed until reconstructed; Trumbull, southbound lane open, northbound lane closed; Wells Court, open.

    Parking is allowed on side streets a block north and south of Center where Center is closed (Pendleton, Park, Green, Livingston). One lane must remain open always for fire trucks and/or ambulances.

    Area residents seeking information are urged to call the city hotline 894-8302 or contact city liaison team members Patti Stowell, 894-8227 or 892-1896; or Warren Smith, 892-5649; or Hampton Township liaison Johanne Luth, 892-5037. Questions for MDOT should be directed to Louie Tayler, 67101535 or e-mail at TaylorL@mi.gov.###

    Printer Friendly Story View
    Prior Article

    February 10, 2020
    by: Rachel Reh
    Family Winter Fun Fest is BACC Hot Spot for 2/10/2020
    Next Article

    February 2, 2020
    by: Kathy Rupert-Mathews
    MOVIE REVIEW: "Just Mercy" ... You Will Shed Tears, or at Least You Should
    Agree? or Disagree?


    Dave Rogers

    Dave Rogers is a former editorial writer for the Bay City Times and a widely read,
    respected journalist/writer in and around Bay City.
    (Contact Dave Via Email at carraroe@aol.com)

    More from Dave Rogers

    Send This Story to a Friend!       Letter to the editor       Link to this Story
    Printer-Friendly Story View


    --- Advertisments ---
         


    0200 Nd: 04-19-2024 d 4 cpr 0






    12/31/2020 P3v3-0200-Ad.cfm

    SPONSORED LINKS



    12/31/2020 drop ads P3v3-0200-Ad.cfm


    Designed at OJ Advertising, Inc. (V3) (v3) Software by Mid-Michigan Computer Consultants
    Bay City, Michigan USA
    All Photographs and Content Copyright © 1998 - 2024 by OJA/MMCC. They may be used by permission only.
    P3V3-0200 (1) 0   ID:Default   UserID:Default   Type:reader   R:x   PubID:mbC   NewspaperID:noPaperID
      pid:1560   pd:11-18-2012   nd:2024-04-19   ax:2024-04-23   Site:5   ArticleID:3991   MaxA: 999999   MaxAA: 999999
    Mozilla/5.0 AppleWebKit/537.36 (KHTML, like Gecko; compatible; ClaudeBot/1.0; +claudebot@anthropic.com)